In-Depth | Structure | Communication Procedures | Timeline/Schedule | Governing Laws and Authorities | SMUD Team Timeline/ScheduleDownload the overall UARP Relicensing Schedule (197k PDF) To ensure that the statutory and regulatory deadlines for relicensing the UARP are met, and to ensure that the relicensing process is efficient and cost-effective for all Participants, SMUD has developed a schedule for the alternative licensing process. SMUD recognizes that all Participants face constraints on the amount of time, money, and personnel that they can commit to the alternative licensing process, and that those constraints can make it difficult to meet certain deadlines. SMUD has therefore tried to provide as much time as reasonably possible for each of the steps of the alternative process, while also recognizing that delays by any one Participant can impose a serious burden on all the other Participants.
Download a PDF of the UARP Relicensing Timeline (154k PDF)
|
||||||