The Upper American River Project, FERC No. 2101, Application for New
License was submitted to the Federal Energy
Regulatory Commission July 15, 2005. This allows the FERC a
two-year review period prior to the license expiration of July 31, 2007.
Exhibits and Supporting Documents Volume I
- Transmittal Letter
- Initial Statement
- Relicensing Process
-
Glossary
- Exhibit A - Project Description
- Exhibit B - Project Operations
- Exhibit C - Construction
- Exhibit D - Project Economics and Financing
- Exhibit F - Design Drawings (Critical Energy Infrastructure
Information CEII - FERC ONLY. Not available for public distribution)
- Exhibit G - Project Maps Non-Internet Public (NIP) available on
CD only
- Exhibit H - General Information
Preliminary Draft Environmental Assessment (PDEA)
Volume 2A
Appendices to the Preliminary Draft Environmental Assessment Volume 2B